Key Points

Once the bid is approved, the homeowner gets an email invite to join the schedule, which shows the current phase, what's next, who's responsible, and the homeowner's own tasks.
The crew builds a pond in 4 passes: excavation and shelving; liner, filtration, and rockwork; planting and water features; and cleanup and handoff.
About 2 weeks to 1 month after the last day, the designer visits in person to answer the questions that come up once the homeowner has lived with the project.

A lot of the homeowners who call us have already called 3 other contractors, and some of those contractors never returned a call or email. Once you hire us, here’s how you stay updated, from the first day of digging to the last.

You’ll learn:

  • Who answers when you call or email
  • What the project schedule shows and when you get it
  • What happens in your yard from the first day on
  • How other trades fit in
  • How long a build takes
  • What happens on the last day, and after

Who Answers When I Call or Email During My Build?

Someone is in our office at all times to answer phones and emails. You can call or email to ask how your job is going.

You’re talking to our own team, not a call center, and we respond right away.


What Does My Project Schedule Show, and When Do I Get It?

Once you approve the bid, we email you an invite to join your project schedule in Buildertrend. You can open it online or in the app at any time.

The schedule is a Gantt chart, which lays your job out on a timeline. It shows:

  • What phase we’re in
  • What’s to come
  • Who’s responsible for each part
  • Anything you’re responsible for
Crew members digging out a pond in a backyard next to a concrete patio

When the schedule says we’re in the excavation phase, our crew is out digging, like in this photo.

Homeowners tell us the schedule helps them know what to expect and what is going on at their home.


What Happens in My Yard From the First Day On?

On the first day, the designer walks through your yard with our crew and goes over your ideas with them.

Here is the order our crew follows for pond construction:

  • Excavation and shelving
  • Liner, filtration, and rockwork
  • Planting and water features
  • Cleanup and handoff

Clients are sometimes surprised that it looks like a bomb went off in their backyard on the first day, but the yard comes together quickly from there.

Our team also comes by throughout the project to check on progress. The designer comes out at certain times when a part of the job needs extra care.

Two black chairs on a covered patio looking out at a backyard pond and a white house

During the build of our recreation swim pond in Alamo, the homeowner could watch from his upstairs office window as the project unfolded, and said it was fascinating to see everything day by day.


What Happens When Other Trades Are Part of Your Backyard Project?

Backyard pool with a paver deck, tropical plants, and a patio umbrella

On a backyard like this one, with a pool, spa, and paver patio, most of the work is done by subcontractors, or subs. Our own crew builds the ponds and waterfalls.

On a pool job, our crew might be there a day or 2 here and there, because so much of it is subs. Running the schedule and managing the subs is most of our work on a pool job. We’ve had relationships with these subs for 20+ years, so they know what they’re doing, and we trust them.

Because we’re in charge from the start, we know how to direct each sub so all the pieces of the backyard come together. When each sub is hired and managed separately, the pieces are hard to tie together.


How Long Does a Pond or Backyard Build Actually Take?

Here is about how long each kind of job takes:

  • Our small, everyday pond jobs: about 2 to 5 days on site
  • The most complicated ponds: about 6 weeks
  • A pool job: about 1.5 to 2 months, and sometimes longer, just to get the permit before we break ground. The most complicated pool builds take about 3 months.

Other trades can make the whole job longer than our time on site.

Aerial view of a pond with a flagstone patio built right to its edge

Our pondside paradise in Brentwood has a natural flagstone patio finished right to the edge of the pond. We built the pond first, then the flagstone, then finished the pond edge to the patio.

We were on site for a few weeks, but the whole project took around 3 months because we were working with other trades as well.

We cover how timing changes with the seasons in Timing Your Pond So It’s Ready for Summer.


What Happens on the Last Day, and After?

When the work is done, here is how the job wraps up:

  • On the last day, our crew teaches you the basics of running your feature.
  • The designer walks you through the job, including how to use and care for each feature.
  • About 2 weeks to 1 month after the last day, the designer visits in person to make sure you understand how everything works and to answer any questions that come up now that you’ve lived with it.

After handoff, startup follows, with beneficial bacteria and plants filling in until the water balances.

From there, a pond needs little from you. You empty the skimmer basket, often once or twice a week, and add a scoop of beneficial bacteria once a week.


How Do Steady Updates Help After a Bad Contractor Experience?

It can be hard to earn a homeowner’s trust at first when they’ve had a bad experience with a contractor. When homeowners ask what we do differently, we point to constant communication and telling them what’s coming up.

That means you can see the next phase on your schedule before it starts, and you can call the office about a problem or a worry, too. Our clients tell us what they appreciate most is our professionalism and communication.

Our lettered trucks and employees in company shirts show up organized, on time, and with the correct equipment to get the job done. We do it once and do it right, so when you call us about a problem, that should be the last call you need to make.


Ready to Plan Your Pond With California Aqua Pros?

If you’re ready to talk about your pond or backyard project, we’d be glad to hear about it. Fill out our contact form or give us a call.

Frequently Asked Questions

What should I do if I don't hear from the contractor for several days during my pond build?

Call or email our office. Someone is there at all times, and the person who picks up is part of our own team, so you can ask about your job directly and hear back right away. If you'd rather check on your own first, open your schedule online or in the app. It shows which phase is underway and what comes next.

Can I log into the project management software myself to check on progress, or do I have to wait for updates from the crew?

You can check it yourself whenever you like. After you approve the bid, we send an email invite to your project schedule in Buildertrend, and once you join, you can open it online or in the app. It lays your job out on a timeline with the current phase, what's to come, who's responsible, and a few tasks that are yours.

How will I get progress updates, and through what method?

You can open your Buildertrend schedule online or in the app whenever you want to see where things stand. For a personal update, call or email the office. Someone is there at all times to talk through your job with you. We also take consistent photos throughout your project.